Airport Events & Newsletters

Upcoming Projects

Runway Overlay - September 2025

  • Start Date: September 22, 2025
  • End Date: October 30, 2025
  • Contractor: Cactus Construction
  • Funding Source: ADOT Airport Pavement Management System
  • Funding Split: ADOT 90% - City of Glendale 10%

Airport Master Plan Update - October 2025

  • Start Date: October 1, 2025
  • End Date: September 30, 2027
  • Consultant: Coffman Associates
  • Funding Source: FAA - Infrastructure Investment and Jobs Act
  • Funding Split: FAA 95% - ADOT 2.5% - City of Glendale 2.5%

Airfield Lighting and Signage Upgrade (Design Only)

  • Start Date: October 1, 2025
  • End Date: September 30, 2026
  • Consultant: Dibble Associates
  • Construction Bid Date: TBD
  • Funding Source: FAA - Airport Improvement Program
  • Funding Split: FAA 91.06% - ADOT 4.47% - City of Glendale 4.47%

Recently Completed Projects

Box Hangar Parking Rehabilitation

We recently did a 2" mill and overlay of the car parking lots behind the box hangars and at Gate 15. We also added new pavement and drainage at the new EAA hangar.

  • Project Dates: June 27 to July 25, 2025
  • Cost: Approximately $250,000
  • Funding Source: City of Glendale Pavement Preservation fund

Taxiway Seal Coat

We performed crack fill and a seal coat on Taxiway A and all of the connecting taxiways. We also did a 2" mill and overlay on A2 and A8.

  • Project Dates: March 15 to April 30, 2025
  • Cost: Approximately $220,000
  • Funding Source: City of Glendale Pavement Preservation Fund

Newsletters