Upcoming Projects
Runway Overlay - September 2025
- Start Date: September 22, 2025
- End Date: October 30, 2025
- Contractor: Cactus Construction
- Funding Source: ADOT Airport Pavement Management System
- Funding Split: ADOT 90% - City of Glendale 10%
Airport Master Plan Update - October 2025
- Start Date: October 1, 2025
- End Date: September 30, 2027
- Consultant: Coffman Associates
- Funding Source: FAA - Infrastructure Investment and Jobs Act
- Funding Split: FAA 95% - ADOT 2.5% - City of Glendale 2.5%
Airfield Lighting and Signage Upgrade (Design Only)
- Start Date: October 1, 2025
- End Date: September 30, 2026
- Consultant: Dibble Associates
- Construction Bid Date: TBD
- Funding Source: FAA - Airport Improvement Program
- Funding Split: FAA 91.06% - ADOT 4.47% - City of Glendale 4.47%
Recently Completed Projects
Box Hangar Parking Rehabilitation
We recently did a 2" mill and overlay of the car parking lots behind the box hangars and at Gate 15. We also added new pavement and drainage at the new EAA hangar.
- Project Dates: June 27 to July 25, 2025
- Cost: Approximately $250,000
- Funding Source: City of Glendale Pavement Preservation fund
Taxiway Seal Coat
We performed crack fill and a seal coat on Taxiway A and all of the connecting taxiways. We also did a 2" mill and overlay on A2 and A8.
- Project Dates: March 15 to April 30, 2025
- Cost: Approximately $220,000
- Funding Source: City of Glendale Pavement Preservation Fund